The Lafayette Reservoir Tower Gets Its New Top This Fall. The Harder Part Waits for Spring.

The tower at the Res is already about 40 feet shorter, and the new operating house that will cap it is scheduled for November 2026. From the Lakeside Nature Trail, the project will look nearly done once that top is on.

EBMUD's schedule runs much longer. The new top is the last visible step of 2026. Once the season's environmental work window closes, crews leave the tower and don't come back until spring 2027. That return trip covers work most walkers will never see: new underwater slide gates and electric motor operators. EBMUD expects the tower to return to full operation in fall 2027. In short, the visible work at the Res wraps up this season, and the work that matters most to the structure is still ahead.

Thirteen Rings Came Off a Tower Built Too Tall

The tower went up in 1929. The dam's planned height changed during construction, which left the tower 40 feet taller than it needed to be. For almost a century that extra height was simply part of the view. After the Oroville Dam crisis in 2017, the California Division of Safety of Dams tightened its rules. Seismic studies showed the tower could bend or break in a large earthquake, and DSOD required EBMUD to fix both the tower and the conduits at its base. The tower is more than a landmark. It also serves as the dam's spillway, which is why the state treats it as a critical structure.

The $14 million project, paid for by EBMUD ratepayers, solves the problem by taking material away. Crews started in early July. They removed the old operating house first, then lifted 13 concrete rings off the tower stem, aiming to reach the new height by August 21. At the start of August, Bay Area Telegraph reported that the top of the tower was gone and the crane barge was still beside it. A few weeks later, after a site visit on August 21, the outlet described the tower as appearing to be at its final, shortened height. The demolition debris was trucked out using the Acalanes Road onramp and never passed through downtown Lafayette.

EBMUD's project page says the work requires no draining of the reservoir.

A New Top Built to Look Like the Old One

EBMUD says it spent a decade working with dam engineers on a design that keeps the tower's existing look, and its project page shows renderings of the finished tower at high, average and low water levels. The new operating house is metal. Before it goes on, crews have to build new corbels, which are the supports, and a new floor inside the existing tower. EBMUD's August stakeholder update sets November 2026 for the operating house to be finished.

The renderings are worth a look before your next lap. They show the finished tower with 40 feet less height above the water.

EBMUD has also heard from residents who would like a piece of the original. The agency has said it is looking at salvaging material from the old tower to make a historic token for the public, and that it will follow up once there is a formal plan.

The Calendar the Tower Actually Runs On

The schedule is set by the environmental work window, not by when the work looks finished. Here is how EBMUD's published milestones line up:

Period What happens at the tower
March 2026 Construction begins
Early July to about August 21, 2026 Old operating house and 13 concrete rings removed
Fall 2026 Corbels, new floor and metal operating house, scheduled for completion in November
Late fall 2026 Environmental work window closes and tower work pauses
Spring 2027 Crews return to install underwater slide gates and electric motor operators
Fall 2027 Final testing and commissioning, then the tower returns to full operation

The contract runs past even that last row. EBMUD's August 6 board report says the conduit retrofits beneath the dam follow in 2027 and puts contract completion in March 2028. The tower may look finished long before the work around it actually ends.

What That Means for a November Lap

Until the window closes, the tower isn't the only job at the Res. EBMUD is also replacing the Recreation Area's wastewater lift station and related piping, adding a backup generator, a fuel tank and a radio tower, and doing retaining-wall work. That project is scheduled from fall 2025 through fall 2026. EBMUD says both projects are active at the same time through fall, with construction noise and crews near the Lakeside Nature Trail and the barge ramp area.

Here's what this phase looks like on the ground:

  • Equipment crossings on the paved loop. Crews move equipment and materials across the Lakeside Nature Trail to reach the exit road. Flaggers work the main entrance gate and the trail as needed, and EBMUD says to expect occasional 10 to 15 minute delays for walkers and for cars entering or leaving.
  • No planned vehicle closures. EBMUD says the tower project doesn't call for closing the road to cars. Its project page also says some parking spaces are used for equipment storage and the reservoir closes during key construction periods. To get word of a closure before you arrive, use EBMUD's construction alert sign-up.
  • The steep connector. The short, much-used path from the dam down to the Visitor Center and main parking area is being rebuilt as part of the tower project. Bay Area Telegraph reported that the road had to be widened locally for heavy equipment, which created a chance to redo the cramped, worn walkway next to it.
  • Recreation stays open. EBMUD says fishing, hiking and picnicking stay available during construction, with changing conditions near the work sites.

On the water, EBMUD's recreation page lists rowboat and pedal-boat rentals from park opening until 4 p.m., with every boat docked by 5 p.m. Personal hand-launch boats follow the same 4 p.m. launch cutoff and 5 p.m. off-the-water time. Fishing permits and boat check-in go through the Visitor Center. On short November afternoons, that cutoff comes well before the light fades.

The Detour That Outlasts the Tower

Walkers who leave the Res for the Walter Costa Trail will run into a different timeline. A 0.3-mile section of the trail through the Lafayette Water Treatment Plant property has been closed since September 2025 and stays closed while the plant improvements continue. Users are sent along a signed street detour. The plant program covers chemical systems, controls, electrical, filtration and disinfection, and EBMUD has scheduled it in phases from 2025 to 2031.

So the tower's winter pause won't make the area construction-free. The Res work is moving into its quiet season, and the plant work next door is only partway through its run. The City of Lafayette's October 30 weekly roundup still lists the reservoir construction as ongoing. For the latest status of any one trail or lot, check EBMUD's Lafayette projects overview and the Lafayette Chamber's reservoir page, where EBMUD posts its stakeholder updates.

Pablo Tiscareno is based in Lafayette and follows changes like the new top on the Res tower, because they shape the views and daily routines that neighbors notice when they think about their homes. If you'd like to talk about how your place looks and lives today, Tiscareno Homes offers a complimentary staging and market consultation whenever you're ready.